Question
The project is to install new sinks in 150 apartment units. The project has a budget of $75,000 and a schedule of 15 weeks. You
The project is to install new sinks in 150 apartment units. The project has a budget of $75,000 and a schedule of 15 weeks.
You just finished week 5 and you have 60 rooms completed, you've spent $50,000 and according to the baselines you're expected to have completed $24,750 worth of work.
Using Earned Value metrics, produce a status/progress report by determining the following, and then summarize the health of the budget and schedule:
BAC =
PV =
EV =
AC =
CV =
CPI =
SV =
SPI =
EAC =
EAC =
ETC =
The project is (under, on, over) ______ budget and (behind, on, ahead of) _______ schedule.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started