The project manager at a software company predicts a project's costs based on previous projects that were similar to the current project. What type of
The project manager at a software company predicts a project's costs based on previous projects that were similar to the current project. What type of cost estimating are they using?
a Parametric
b Analogous
c Bottomup
d Rolling wave