The project manager explains that if one of the risks in the project is accepted, the project team can save at least 20% of the
The project manager explains that if one of the risks in the project is accepted, the project team can save at least 20% of the project time. However, it would increase the expenses by 5%. On what basis should the top management make a decision on this project? Group of answer choices Credibility of the project manager Past project experiences Risk tolerance level Credibility of project team