The Project Manager for the development of a client's data center is working with her project team to develop the project's WBS . She shows
The Project Manager for the development of a client's data center is working with her project team to develop the project's WBS She shows her team how to break down the Project Scope into WBS components but her team is having trouble understanding how far down the breakdown effort should go She plans to inform her team what the lowest level item in a WBS is What is the answer she will provide?Group of answer choicesA DeliverableA Leaf ObjectAn ActivityA Work Package