Question
1 Approved Answer
The project manager should stop crashing the project as soon as Group of answer choices One of the nodes has negative slack. There are multiple
The project manager should stop crashing the project as soon as Group of answer choices One of the nodes has negative slack. There are multiple critical paths. The new deadline has been met or the incremental cost of crashing further outweighs the savings in penalty cost or monetary bonus achieved. All of the activities have zero slack. All of the activities are at their minimum, crash values