The project represented by this network diagram has activity lengths in days and crash costs as shown in the table. The fixed cost for being
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table. The fixed cost for being on site is $450. What is the lowest total completion cost for the project?
Activity | Original Length | Maximum Reduction | Crash Cost/Day |
A | 1 | 0 | -- |
B | 9 | 2 | $475 |
C | 4 | 1 | $350 |
D | 8 | 2 | $500 |
E | 10 | 2 | $425 |
F | 4 | 1 | $300 |