The project starts with tasks A and I. At the completion of task A, both tasks B and D may start. The task C follows
The project starts with tasks A and I. At the completion of task A, both tasks B and D may start. The task C follows B and I. The task E follows D. The tasks G and H can start at the completion of task E. The task F can start after completion of task C and E. The project is finished after completion of task F,G and H 1. Construct a PERT/CPM network for the project