Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The project team has started the risk management plan and needs now to identify, assess, and manage the project risks. In order to identify individual
The project team has started the risk management plan and needs now to identify, assess, and manage the project risks. In order to identify individual project risks, the team will examine those tasks on the project schedule with potential issues during their execution.
The Project Manager has asked their team to go over the instructions to complete the risk register and identify four negative and two positive risks.
Doubleclick the Risk Register on the next page and follow the instructions presented in Table A below to complete this assignment
Table A: Instructions to Complete the Risk Register
Process Instructions
Identify Risks Task Name: Using the project schedule you developed in Week select a task and enter it in the risk register.
Risk Identified: Ask yourself the question: What can go wrong during the execution of the task? Describe the risk you have identified.
Assess Risks Probability: Ask yourself the question: What is the likelihood of occurrence of the identified risk in the task you have selected?
Enter a number between and When the probability of occurrence is very high enter a high enter a medium enter a low enter a very low enter a
Impact: Ask yourself the question: What will be the risk impact on the project objectives if the identified risk occurs? Enter a number between and in the Impact columns. When the impact on the project objective is Very High enter a ; when the Impact is High enter a ; when the Impact is Medium enter a ; when the Impact is Low enter a or when the impact is Very low enter a
Risk Score: The Risk Score is calculated by multiplying the Probability of occurrence P times the risk Impact I
Plan
Risk Response
Risk Owner: The risk owner is a subject matter expert SME from the core team, PMO, or from a different department who is familiar with the project task. Therefore, the risk owner is suitable to create a risk response plan. Enter the risk owner for each identified risk. Use the dropdown menu for this cell
Risk Strategy or : This column presents Risk response strategies for negative & positive risks. Select a suitable risk strategy for positive and negative risks, using the dropdown menu in the cell.
Strategies for negative risks include the Escalate, Avoiding, Transferring, Mitigating, & Accept risk strategies.
Strategies for positive risks include the Escalate, Enhance, Exploit, Share, & Accept riskFor a demonstration of how to create a risk register, please view the Risk Register video in the Course Project Overview.
Tiny House Project Risk Register for Negative RiskTHE TINY HOUSE PROJECT
Risk Management Due Week
The project team has started the risk management plan and needs now to identify, assess, and manage the project risks. In order to identify
individual project risks, the team will examine those tasks on the project schedule with potential issues during their execution.
The Project Manager has asked their team to go over the instructions to complete the risk register and identify four negative and two positive
risks.
Doubleclick the Risk Register on the next page and follow the instructions presented in Table A below to complete this assignment
Table A: Instructions to Complete the Risk Register
For a demonstration of how to create a risk register, please view the Risk Register video in the Course Project Overview.Tiny House Project Risk Register for Negative Risk
tabletableIDENUFYRISKtablePERFORM QUALITATIVERISK ASSESSMENTPLAN RISK RESPONSEIDTask Name,tableRisk IdentifiedDescriptionProb.,Impact,tableRiskScoretableRiskOwnertableRiskStrategyRisk Response PlanNEGATIVE RISKPOSITIVE RISKS
Risk score is calculated from the probability times the highest risk score.
table to to to Risk Marnagement Due Week
The projact teom has storted the risk monogement plon and noods now to identify, aseess, and monoge the projact risks. In order to identify
individuol project risks, the teom wil examine those tosks on the project schadule with potantiol eseues during their axecution.
The Projact Monoger has osked their toom to po our the instructions to complete the risk reqister and identify four nogotive and two positive
risks.
Table A: instructions to Complete the Risk Register
Tiny House Project Riak Register for Negetive Riak
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started