The proposed expansion of CIV Electronics' plant facilities requires the immediate outlay of $95,000. Expected net returns are given in the following table. Calculate the
|
The proposed expansion of CIV Electronics' plant facilities requires the immediate outlay of
$95,000.
Expected net returns are given in the following table. Calculate the internal rate of return (IRR).
Year 1 | $Nil | Year 4 | $58,000 | |
Year 2 | $21,000 | Year 5 | $46,000 | |
Year 3 | $33,000 | Year 6 | $17,000 |