Question

1 Approved Answer

The Pullman Mfg . , Inc. three - station work cell illustrated in the figure below has two machines at station 1 in parallel. (

The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.)
The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3.
a) The throughput time of the new work cell is 36 minutes (enter your response as a whole number).
b) The bottleneck time of the new work cell is 10TT minutes per unit (enter your response as a whole number).
c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 3 is units (enter your response as a whole number)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions

Question

15. What are three limitations of control group designs?

Answered: 1 week ago