The Pullman Mfg . , Inc. three - station work cell illustrated in the figure below has two machines at station 1 in parallel. (

The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel.(The product needs to go through only one of the two machines before proceeding to station2.)
Station 1
Machine A
Station 1
Machine B
Station 2
Station 3
12 min/unit
12 min/unit
12 min/unit
2 min/unit
A three-station work cell has a product that must go through one of the two machines at station 1(they are parallel) before proceeding to station 2 and then on to station 3. Both Machine A and Machine B at Station 1 take 12 minutes per unit. Station 2 takes 12 minutes per unit. Station 3 takes 2 minutes per unit.
The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station .
Part 2
a) The throughput time of the new work cell is
enter your response here minutes (enter your response as a whole number).
Part 3
b) The bottleneck time of the new work cell is
enter your response here minutes per unit (enter your response as a whole number).
Part 4
c) If the firm operates hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation is
enter your response here units(enter your response as a whole number).
Part 5
d) If the firm operates hours per day, 6 days per week, the weekly capacity of the work cell without the second machine at workstation is
enter your response here units(enter your response as a whole number).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Art Of Bad Management

Authors: Nathan Burden

1st Edition

1980615551, 978-1980615552

More Books

Students also viewed these General Management questions

Question

What are the role of supervisors ?

Answered: 1 week ago