The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes. The accompanying table
The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes. The accompanying table shows the activities, times, and sequences required: | ||||||||||
Time in days | ||||||||||
Activity | Immediate Predecessor | Optimistic | Most Likely | Pessimistic | ||||||
A | - | 3 | 6 | 8 | ||||||
B | A | 2 | 4 | 4 | ||||||
C | A | 1 | 2 | 3 | ||||||
D | C | 6 | 7 | 8 | ||||||
E | B,D | 2 | 4 | 6 | ||||||
F | B | 6 | 10 | 14 | ||||||
G | E, F | 1 | 2 | 4 | ||||||
H | F | 3 | 6 | 9 | ||||||
I | G | 10 | 11 | 12 | ||||||
J | H, I | 14 | 16 | 20 | ||||||
a. Draw the network diagram with EF, ES, LS, and LF noted. (Hint: Pick one of the three processing times above.) | ||||||||||
b. What is the critical path? | ||||||||||
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten and why? | ||||||||||
d. What is the new critical path and the earliest completion time? |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started