Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes. The accompanying table

The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes. The accompanying table shows the activities, times, and sequences required:
Time in days
Activity Immediate Predecessor Optimistic Most Likely Pessimistic
A - 3 6 8
B A 2 4 4
C A 1 2 3
D C 6 7 8
E B,D 2 4 6
F B 6 10 14
G E, F 1 2 4
H F 3 6 9
I G 10 11 12
J H, I 14 16 20
a. Draw the network diagram with EF, ES, LS, and LF noted. (Hint: Pick one of the three processing times above.)
b. What is the critical path?
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten and why?
d. What is the new critical path and the earliest completion time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions

Question

LO14.1 Describe the characteristics of oligopoly.

Answered: 1 week ago