The R\&D department is planning to bid on a large project for the development of a new communication system for commercial planes The accompanying table shows the activities, times, and sequences required: b. What is the critical path? Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. b. What is the critical path? Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correc answer and double click the box with the question mark to empty the box for a wrong answer. A.C.F.G-1 A-B-E-1 A.D.H-I A-D.F.G-I c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D and G each one week. Which would you shorten? Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten? Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. d-1. What is the new critical path? Note: You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. A.C.F.G.I A-B.E-1 A-D + H-1 A.D.F.G-1 d-2. What is the earliest completion time for the new critical path