Question
The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table
The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, time & sequence required:
Activity | Immediate predecessor | Time (weeks) |
A | --- | 3 |
B | A | 2 |
C | A | 4 |
D | A | 4 |
E | B | 6 |
F | C,D | 6 |
G | D,F | 2 |
H | D | 3 |
I | E,G,H | 3 |
A. Draw the Network Diagram
B. What is the critical path?
C. Suppose you want to shorten the completion time as much as possible, & you have the option of shortening any or all of B,C,D, and G each one week. Which would you shorten?
D. What is the new critical path & earliest completion time?
Please solve using Microsoft Excel & show any work if possible. Thanks!
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started