The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag? a Start
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag? a Start to Finish b Start to Start c Finish to Finish d Finis