The return expected from Project No. 542 is 28 percent. The standard deviation of these returns is 14 percent. Use the Table V to answer
The return expected from Project No. 542 is 28 percent. The standard deviation of these returns is 14 percent. Use the Table V to answer the following questions. If returns from the project are normally distributed, what is the chance that the project will result in a rate of return above 42 percent? Round your answer to two decimal places.
%
What is the probability that the project will result in losses (negative rates of return)? Round your answer to two decimal places.
%
Step by Step Solution
There are 3 Steps involved in it
Step: 1