The revised estimate at completion ( EAC = A C + ETC assumes that: a . The rate of delivering work in the future is
The revised estimate at completion EACETC assumes that:
a The rate of delivering work in the future is the same as that to date.
b The delivery of future work will match its cost estimates.
c Future work will be delivered at the same efficiency of past work.
d There will be no further delays to project work.