The right of way and the road bed for a new highway will cost $4.5 million.The pavement will cost $2.5 million and it has a
The right of way and the road bed for a new highway will cost $4.5 million.The pavement will cost $2.5 million and it has a much shorter life of 20 years. if the discount rate is 9% find the projects capitalized cost?