The savvy project manager knew there would be a high demand for finish carpenters in late October, so she started a crew early on one
The savvy project manager knew there would be a high demand for finish carpenters in late October, so she started a crew early on one section of the house so they would be available to help elsewhere later on This project manager is engaging in:
Question Select one:
A
resource allocation.
B
resource scheduling.
C
resource acquisition.
D
resource leveling.