The schedule data in weeks for a project is shown below. Using the Activity on Node ( AON ) approach ( and assuming that the
The schedule data in weeks for a project is shown below. Using the Activity on Node AON approach and assuming that the Earliest Start Time for Activity is ZERO which of the following answers is correct:
Activity Duration Dependencies
NA
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
The Total Float for Activity is weeks and for Activity is weeks
The Critical Path for the project is Activities
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started