Question

1 Approved Answer

The scope of work of the contract includes coordination with other entities, public utilities, etc., entities over which neither you or the owner have any

The scope of work of the contract includes coordination with other entities, public utilities, etc., entities over which neither you or the owner have any control, to complete the project. What strategies would be helpful to facilitate getting the necessary utility work done promptly to avoid delays for the contractor? 


a. Call the utility company a week before you need their work installed to keep your project moving 


b. Invite representatives from the public utility companies to the pre-construction meeting 


c. Contact utility companies early in the project life cycle; preferably during pre-design to determine all regulatory requirements, and permitting, and provide all design documents and utility requirements 


d. Invite representatives from the public utility companies to attend regular progress meetings and practice ongoing partnering to accomplish required tasks

Step by Step Solution

3.36 Rating (162 Votes )

There are 3 Steps involved in it

Step: 1

The detailed answer for the above question is provided below c Contact utility compa... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Database Management

Authors: Jeff Hoffer, Ramesh Venkataraman, Heikki Topi

12th edition

133544613, 978-0133544619

More Books

Students also viewed these General Management questions

Question

Discuss the differences between triggers and stored procedures.

Answered: 1 week ago