The scrum team and the stakeholders are meeting at the end of a sprint. They are discussing the sprint goal and the PBIs selected. The
The scrum team and the stakeholders are meeting at the end of a sprint. They are discussing the sprint goal and the PBIs selected. The team demonstrates the product and answers any questions. In which formal event is this done? Select an answer: sprint retrospective sprint review product backlog refinement sprint planning