The setup time in a sequential batch production operation is 2.0 hr, and the actual process- ing time is 1.60 min per cycle. Three

The setup time in a sequential batch production operation is 2.0 hr, and the actual process- ing time is 1.60 

The setup time in a sequential batch production operation is 2.0 hr, and the actual process- ing time is 1.60 min per cycle. Three parts are produced each cycle. No tool handling time is included in the cycle. Part handling time each cycle is 45 sec. It consists of the worker obtaining two starting work units from a parts tray, loading them into the machine, and then after processing, unloading the completed parts and placing them into the same tray. Each tray holds 24 parts. When all of the starting work units have been replaced with completed parts, the tray of completed parts is moved aside and a new tray of starting units is moved into position at the machine. This irregular work element takes 4.0 min. Batch quantity is 2,400 units. Determine (a) average cycle time, (b) time to complete the batch, and (c) aver- age production rate.

Step by Step Solution

3.47 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

a Average cycle time Actual processing time per cycle 160 min Part handling time per cycle 45 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting Information for Decision-Making and Strategy Execution

Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young

6th Edition

137024975, 978-0137024971

More Books

Students also viewed these General Management questions