The Smitty's Company is involved in a three-year long-term contract. The following data relate to this contract: 2019 2020 2021 Total Contract Price $ 200,000
The Smitty's Company is involved in a three-year long-term contract. The following data relate to this contract: | |||||
2019 | 2020 | 2021 | Total | ||
Contract Price | $ 200,000 | ||||
Costs incurred each year | $ 24,000 | $ 56,000 | $ 30,000 | $ 110,000 | |
Costs incurred to date | $ 24,000 | $ 80,000 | $ 110,000 | ||
Estimated cost to complete | $ 96,000 | $ 40,000 | $ - | ||
Partial billings each year | $ 50,000 | $ 112,000 | $ 38,000 | ||
Cash collected from billings | $ 35,000 | $ 120,000 | $ 45,000 | ||
Prepare the journal entries for each of the following assuming Smitty's Company satisfies its performance obligation. | |||||
2019, 2020, and 2021 Entries | |||||
(.) Construction costs for the year | |||||
(.) Partial billings | |||||
(.) Cash collections | |||||
(.) Gross Profit |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started