The standard cost of product 2525 includes 2.65 hours of direct labour at $14.55 per hour. The predetermined overhead rate is $22.30 per direct labour

The standard cost of product 2525 includes 2.65 hours of direct labour at $14.55 per hour. The predetermined overhead rate is $22.30 per direct labour hour. During July, the company incurred 4,440 hours of direct labour at an average rate of $14.85 per hour and $92,452 of manufacturing overhead costs. It produced 1,600 units.

a. Calculate the total, price, and quantity variances for labour.

b. Calculate the total overhead variance.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Management Control Systems Text And Cases

Authors: Kenneth A. Merchant

1st Edition

0135541557, 978-0135541555

More Books

Students also viewed these Accounting questions

Question

Draw a labelled diagram of the Dicot stem.

Answered: 1 week ago