If your CV is RM 10,000, your SV is -RM 3,000 and your PV is RM 100,000? Determine: a. Schedule Performance Index b. Actual Cost
If your CV is RM 10,000, your SV is -RM 3,000 and your PV is RM 100,000? Determine:
a. Schedule Performance Index
b. Actual Cost