The standard costs and actual costs for direct labor in the manufacture of 2,500 units of product are as follows: Standard Costs Direct labor 7,500
The standard costs and actual costs for direct labor in the manufacture of 2,500 units of product are as follows:
Standard Costs Direct labor 7,500 hours at $11.80
Actual Costs Direct labor 7,400 hours at $11.40
The direct labor time variance is
a.$1,140 favorable
b.$1,180 unfavorable
c.$1,140 unfavorable
d.$1,180 favorable