Question
The standard costs for product AX14 are: Direct materials: 40 yards at $3.70 per yard $148 Direct labor: 7 hours at $18.00 per hour 126
The standard costs for product AX14 are:
Direct materials: 40 yards at $3.70 per yard | $148 |
Direct labor: 7 hours at $18.00 per hour | 126 |
Total | $274 |
The following information pertains to August: Direct material purchased and used: 42,500 yards for $148,750 Direct labor: 7,500 hours for $136,500 Actual completed production: 1,050 units Required: Calculate the following variances:
A) direct-material purchase price variance, B) direct-material quantity variance, C)direct-labor rate variance and D) direct-labor efficiency variance. Indicate whether each variance is favorable or unfavorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Lets break down the variances for product AX14 A DirectMaterial Purchase Price Variance Actual Co...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Cost Accounting
Authors: William K. Carter
14th edition
759338094, 978-0759338098
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App