Question

1 Approved Answer

The standard factory overhead rate is $12 per machine hour ($10 for variable factory overhead and $2 for fixed factory overhead) based on 100% capacity

The standard factory overhead rate is $12 per machine hour ($10 for variable factory overhead and $2 for fixed factory overhead) based on 100% capacity of 42,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 2,000 units were as follows:

Actual: Variable factory overhead $350,500
Fixed factory overhead 84,000
Standard: 35,000 hours @ $12 420,000

Determine the (a) volume variance, (b) controllable variance, and (c) total factory overhead cost variance.

a. Volume variance $
b. Controllable variance $
c. Total factory overhead cost variance $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

What is one of the skills required for independent learning?Explain

Answered: 1 week ago