The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:

Actual: Variable factory overhead $360,000

Fixed factory overhead 104,000

Standard hours allowed for units produced: 60,000 hours

What is the amount of the variable factory overhead controllable variance?

a.$14,000 unfavorable

b.$12,000 favorable

c.$26,000 unfavorable

d.$12,000 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Accounting

Authors: Claudia Gilbertson

10th Edition

1111581169, 978-1111581169

More Books

Students also viewed these Accounting questions