The standard time and rate for one unit of a product are as follows: Standard Time 12 hours Standard rate Sh.5 per hour The actual

The standard time and rate for one unit of a product are as follows:

Standard Time 12 hours

Standard rate Sh.5 per hour

The actual data and related information are as under:

Actual production 1,000 units

Actual time 13,200 Hours

Total actual wages Sh.59,400

Required: Calculate Labour cost variance, Labour efficiency variance and Labour rate variance from the above information

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Assurance Services

Authors: Timothy Louwers, Penelope Bagley, Allen Blay, Jerry Strawser, Jay Thibodeau

9th International Edition

1266285997, 978-1266285998

More Books

Students also viewed these Accounting questions