The supply chain manager for Keskin Industries, Sean Willems, has developed the data shown in the table below for two vendors. Later Sean Willems has found a third possible vendor. He now wants to evaluate all three vendors using the weights provided in the table below. He scores the third vendor, Fricker V-Tech, Ltd., as: Engineering Competence 4, Process Capability 5, Cost 1, Quality 2, Performance to Schedule 4, and After-Sales Service 2. Click the icon to view the additional information. The weighted total for Joglekar Technology is (enter your response as a whole number). to 100), not percentages, so each supplier's expressed in whole units (that sum . so each supplier's total score will be between 100 and 500 . Notice that the weights in this problem are expressed in whole units (that sum to 100), not percentages, so each supplier's total score will be between 100 and 500 . The supply chain manager for Keskin Industries, Sean Willems, has developed the data shown in the table below for two vendors. Later Sean Willems has found a third possible vendor. He now wants to evaluate all three vendors using the weights provided in the table below. He scores the third vendor, Fricker V-Tech, Ltd., as: Engineering Competence 4, Process Capability 5, Cost 1, Quality 2, Performance to Schedule 4, and After-Sales Service 2. Click the icon to view the additional information. The weighted total for Joglekar Technology is (enter your response as a whole number). to 100), not percentages, so each supplier's expressed in whole units (that sum . so each supplier's total score will be between 100 and 500 . Notice that the weights in this problem are expressed in whole units (that sum to 100), not percentages, so each supplier's total score will be between 100 and 500