The table below gives durations of the remaining 10 tasks of an overdue project. There is only one machine to process these tasks. Until the

The table below gives durations of the remaining 10 tasks of an overdue project. There is only one machine to process these tasks. Until the project is completed, the factory needs to pay a penalty of $100 per day. A manager suggests to rent a second identical machine, at a fee of $80 per day, to reduce the project finishing time (makespan) and thus the penalty payment.

image text in transcribed

1. Determine the makespan and total penalty cost in the single machine case.

2. With a second machine, how would you schedule these tasks to minimize the project completion time? Present you schedule and determine the finish time of each machine.

3. Decide whether you want to rent the second machine by comparing the total cost with the single machine case.

4. In general, LST+LPT rule does not guarantee to minimize the makespan in all cases. But for this particular problem, the resulting makespan is the minimum one. Explain why.

C A | 8 B 3 4 D 6 E 15 F 10 G 12 H 7 I 9 J 4 C A | 8 B 3 4 D 6 E 15 F 10 G 12 H 7 I 9 J 4

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Healthcare Finance

Authors: Paula H. Song, Kristin L. Reiter

4th Edition

1640553223, 978-1640553224

More Books

Students also viewed these Finance questions