The table below includes processing times and due dates for five jobs. Processing Days Due Time (days) From Today Job 12 23 14 20 30
The table below includes processing times and due dates for five jobs. Processing Days Due Time (days) From Today Job 12 23 14 20 30 26 28 18 10 Using the earliest due date (EDD), the average flow time is (Points 25) O approximately 36 days O approximately 26 days O approximately 28 days O approximately 22 days