The table below provides the parameters for a new current state value stream map for the family of retainers at the Jensen Bearings Inc. firm
The table below provides the parameters for a new current state value stream map for the family of retainers at the Jensen Bearings Inc. firm described in the chapter. This table depicts the value stream after Kline Steel agrees to accept daily orders for steel sheets and also agrees to deliver on a daily basis. Calculate each component of the new value stream's reduced lead time. Jensen Bearings operates 5 days per week.
Overall Process Attributes | Average demand: 2 comma 7002,700/week (1 comma 5001,500 "L";1 comma 2001,200 "S")Batch size: 1,000 Number of shifts per day: 1 Availability: 8 hours per shift with two 30 minute lunch breaks | |
Process Step 1 | Press | Cycle timeequals=55 secondsSetuptimeequals=2 hoursUptimeequals=90% Operatorsequals=1 Every PartEveryequals=1 weekWIPequals=11 day of sheets (before Press) |
Process Step 2 | Pierce & Form | Cycle timeequals=2727 secondsSetuptimeequals=30 minutesUptimeequals=100% Operatorsequals=1 WIPequals=1 comma 1001,100 "L",1 comma 2501,250 "S" (before Pierce & Form) |
Process Step 3 | Finish Grind | Cycle timeequals=3737 secondsSetuptimeequals=45 minutesUptimeequals=100% Operatorsequals=1 WIPequals=200200 "L",1 comma 4501,450 "S" (before Finish Grind) |
Process Step 4 | Shipping | WIPequals=400400 "L",1 comma 1001,100 "S" (after Finish Grind) |
Supplier Information | One shipment a day in trays of 60 pieces | |
Information Flow | All communications from customer are electronic: 180/90/60/30/day Forecasts Daily Order All communications to supplier are electronic 4-week Forecast Weekly Fax There is a weekly schedule manually delivered to Press, Pierce & Form, and Finish Grind and a Daily Ship Schedule manually delivered to Shipping All material is pushed |
Click the icon to view the data from the new current state value stream map at Jensen Bearings Inc.
a. How many days of raw material does the Bearing's plant now hold?
The plant holds
11
days of raw material. (Enter your response rounded to one decimal place.)
b. How many days of work in process inventory is held between Press and Pierce & Form?
The inventory is held
nothing
days. (Enter your response rounded to one decimalplace.)
c. How many days of work in process inventory is held between Pierce & Form and Finish Grind?
The inventory is held
nothing
days. (Enter your response rounded to one decimalplace.)
d. How many days of work in process inventory is held between Finish Grind andShipping?
The inventory is held
nothing
days. (Enter your response rounded to one decimalplace.)
e. What is the new value stream's production lead time?
The production lead time is
nothing
days. (Enter your response rounded to one decimalplace.)
f. What is the new value stream's processing time?
The processing time is
nothing
seconds. (Enter your response as a whole number.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started