The table below shows the activities of one of the projects with direct costs and the usual and compressed periods, according to the contract, the

The table below shows the activities of one of the projects with direct costs and the usual and compressed periods, according to the contract, the project must be completed within seven weeks. Find the lowest cost for the project if you know that the indirect costs are (($ 100 / week), and the late penalty is $ (50) $ 7 a week *

image text in transcribed

Activity Preceded By A B D E F Normal Crash Time (weak) Cost (S) Time (weak) Cost (S) 2 100 1 150 + 120 3 140 2 70 1 110 3 90 2 110 2 100 1 160 2 140 1 200 3 30 2 50 3 60 3 60 + 40 3 70 3 100 1 160 2 200 1 260 B B H 1 J D E,F GH Activity Preceded By A B D E F Normal Crash Time (weak) Cost (S) Time (weak) Cost (S) 2 100 1 150 + 120 3 140 2 70 1 110 3 90 2 110 2 100 1 160 2 140 1 200 3 30 2 50 3 60 3 60 + 40 3 70 3 100 1 160 2 200 1 260 B B H 1 J D E,F GH

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions