Question
1 Approved Answer
The takt time, or per unit cycle time required to meet demand, for the given customer demand during the simulation was Demand =60 sheets; Time
The takt time, or per unit cycle time required to meet demand, for the given customer demand during the simulation was Demand =60 sheets; Time available =15 minutes Please input your answer in number of seconds per sheet. For example, if the correct answer is 20 seconds/sheet, simply input 20
Step by Step Solution
There are 3 Steps involved in it
Step: 1