The task is following. Use data for the following project: Activity Duration, weeks Predecessor A Design/Funding 8 B Allocate/Renovate Office Space 12 A C Order
The task is following. Use data for the following project: Activity Duration, weeks Predecessor A Design/Funding 8 B Allocate/Renovate Office Space 12 A C Order Servers and Network Switches 8 A D Build Network 12 B,C E Order Software 4 B,C F Setup Firewall 4 E G Test network under full load 8 F,D 1. Create Gantt chart for the schedule; 2. Identify Critical time and time Critical Path ; 3. Construct / draw AOA network. Upload Excel File with the solved