The task times of 12 independent tasks T1 to T12 are given, in minutes, as
2, 7, 4, 10, 10, 3, 3, 6, 11, 5, 8, 9
Use the list processing algorithm to schedule these tasks on three processors, #1, #2, and #3. The tasks are prioritized in the order written above. (a) Which of these tasks does processor #1 complete?
T1 T2 T3 T4 T5 T6 T7 T8 T9 T10 T11 T12
(b) Which of these tasks does processor #2 complete?
T1 T2 T3 T4 T5 T6 T7 T8 T9 T10 T11 T12
(c) Which of these tasks does processor #3 complete?
T1 T2 T3 T4 T5 T6 T7 T8 T9 T10 T11 T12
(d) Is the schedule optimal?
Need more information to decide, No or Yes
(e) How long is an optimal schedule for these 12 tasks? ____ minutes
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started