The T-bill rate is 4 percent, and the expected return on the market is 12 percent. Which
Fantastic news! We've Found the answer you've been seeking!
Question:
The T-bill rate is 4 percent, and the expected return on the market is 12 percent.
Which projects have a higher expected return than the firm's 12 percent cost of capital?
Which projects should be accepted?
Which projects will be incorrectly accepted or rejected if the firm's overall cost of capital were used as a hurdle rate?
project Beta IRR
W .80 10.2%
X .90 11.4
Y 1.10 12.6
Z 1.35 15.1