The total activity time required to perform the tasks at each station are as follows: Station: Total Activity Time Station 1: 6 minutes Station 2:
The total activity time required to perform the tasks at each station are as follows: | ||||||
Station: | Total Activity Time | |||||
Station 1: | 6 minutes | |||||
Station 2: | 7 minutes | |||||
Station 3: | 2 minutes | |||||
Station 4: | 6 minutes | |||||
Station 5: | 10 minutes | |||||
Station 6: | 5 minutes | |||||
A. Which station is the bottleneck? Explain.
B. This production line has capacity to produce how many units per hour? (In the long run, not counting the time that would be required for the first unit to pass through an empty system at startup.) SHOW YOUR WORK.
C. What is the efficiency of the line? SHOW YOUR WORK.
If the activities in this line could be re-balanced (rearranged among the six workstations, keeping the same total activity time across the entire line), what is the maximum hourly production rate that could achieved with six stations? SHOW YOUR WORK
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started