The total budget for the project is $137,200. The manager became concerned when he saw that the project cost so far as $110,420 and was

The total budget for the project is $137,200. The manager became concerned when he saw that the project cost so far as $110,420 and was worried about the progress of the project. Manager has calculated the value of the work completed ($87,150 at original budget rates) and checked the value of the work he should have completed by now ($97,920 at original budget rates).

What are the values of the PV (Planned Value), EV (Earned Value) and AC (Actual Cost)?

Calculate the schedule variance, cost variance and forecasted total cost at completion

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management A Competitive Advantage Approach Concepts

Authors: Fred R. David, Forest R. David

15th edition

978-0133444896, 133444791, 9780133444858, 133444899, 133444856, 978-0133444797

More Books

Students also viewed these General Management questions

Question

What might be a problem of long-term treatment with chloroquine?

Answered: 1 week ago