The total budget for your project is $4,200,000. You need to work out a new forecast for what your budget situation will be like at
The total budget for your project is $4,200,000. You need to work out a new forecast for what your budget situation will be like at project completion.. You've now spent a total of $2,625,000. You look at all of the activities done by the team and you find that the project is 70% complete. Can you come up with a new forecast for your project. Calculate EV, CPI, EAC, ETC, VAC, TCPI