Question
1 Approved Answer
The total project cost includes project direct cost and indirect cost. The (indirect) cost associated with sustaining the project is $4,000 per week. What is
The total project cost includes project direct cost and indirect cost. The (indirect) cost associated with sustaining the project is $4,000 per week. What is the optimal crashing plan? Calculate the lowest total project cost.
Activity A B C D E F G H I Immediate Predecessor None A A C B, D E, F F G, H Normal Time (Weeks) 9 5 3 6 4 7 5 6 8 Crash Time (Weeks) 6 3 2 4 2 4 4 2 5 Total: Normal Cost S 20,000 6,000 15,500 32,000 5,000 17,500 30,000 26,000 40,000 $192,000 Crash Cost $ 35,000 9,000 20,000 36,000 10,000 25,000 34,000 30,000 58,000 $257,000 Activity A B C D E F G H I Immediate Predecessor None A A C B, D E, F F G, H Normal Time (Weeks) 9 5 3 6 4 7 5 6 8 Crash Time (Weeks) 6 3 2 4 2 4 4 2 5 Total: Normal Cost S 20,000 6,000 15,500 32,000 5,000 17,500 30,000 26,000 40,000 $192,000 Crash Cost $ 35,000 9,000 20,000 36,000 10,000 25,000 34,000 30,000 58,000 $257,000
Step by Step Solution
★★★★★
3.43 Rating (159 Votes )
There are 3 Steps involved in it
Step: 1
ANSWER To determine the optimal crashing plan and calculate the lowest total project cost we need to calculate the cost and time savings for each activity when crashed Lets calculate the crashing savi...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started