Question

1 Approved Answer

The values for Standard quantity or hours are incorrect. So are some of the values on the third picture. Please show how you got the

image text in transcribedimage text in transcribedimage text in transcribed

The values for Standard quantity or hours are incorrect. So are some of the values on the third picture.

Please show how you got the answers also.

Problem 10-10 Multiple Products, Materials, and Processes [LO10-1, LO10-2] Mickley Corporation produces two products, Alphabs and Zeta7s, which pass through two operations, Sintering and Finishing. Each of the products uses two raw materials-X442 and Y661. The company uses a standard cost system, with the following standards for each product (on a per unit basis): Product Alpha 6 Zeta7 Raw Material X442 Y661 1.2 kilos 2.0 liters 3.0 kilos 4.0 liters Standard Labor Time Sintering Finishing 0.40 hours 0.80 hours 0.10 hours 0.60 hours Information relating to materials purchased and materials used in production during May follows: Material X442 Y661 Purchases 14,500 kilos 15,500 liters Purchase Cost $60,900 $27,900 Standard Price $4.00 per kilo $1.90 per liter Used in Production 9,000 kilos 13,500 liters The following additional information is available: a. The company recognizes price variances when materials are purchased. b. The standard labor rate is $21.00 per hour in Sintering and $19.50 per hour in Finishing. c. During May, 1,250 direct labor-hours were worked in Sintering at a total labor cost of $28,750, and 2,900 direct labor-hours were worked in Finishing at a total labor cost of $62,350. d. Production during May was 2,000 Alphabs and 2,250 Zeta7s. Required: 1. Complete the standard cost card for each product, showing the standard cost of direct materials and direct labor. 2. Compute the materials price and quantity variances for each material. 3. Compute the labor rate and efficiency variances for each operation. Reg 1 Reg 2 Reg 3 Complete the standard cost card for each product, showing the standard cost of direct materials and direct labor. (Round your answers to 2 decimal places.) Standard Quantity or Hours Standard Price or Rate Standard Cost Alpha 6 Direct materials-X442 2,400.00 kilos $ 4.00 per kilo 9,600.00 4,000.00 liters $ 1.90 per liter 7,600.00 800.00 hours $21.00 per hour 16,800.00 1,600.00 hours | $19.50 per hour 31,200.00 Direct labor-Sintering Direct labor-Finishing Total 65,200.00 Zeta: Direct materials-X442 Direct materials-Y661 Direct labor-Sintering Direct labor-Finishing [ 6,750.00 kilos 9,000.00 liters 225.00 hours 1,350.00 hours $ 4.00 per kilo $ 1.90 per liter $ 21.00 per hour $19.50 per hour 27,000.00 17,100.00 4,725.00 26,325.00 Total 75,150.00 Req 1 Reg 2 Reg 3 Compute the materials price and quantity variances for each material. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect i.e., zero variance). Input all amounts as positive values.) 1,800U 600F Direct Materials VariancesMaterial X442: Materials price variance Materials quantity variance Direct Materials Variances-Material Y661: Materials price variance Materials quantity variance 1,350 F 950 U

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cloud Computing Data Auditing Algorithm

Authors: Manjur Kolhar, Abdalla Alameen, Bhawna Dhupia, Sadia Rubab, Mujthaba Gulam

1st Edition

1946983144, 978-1946983145

More Books

Students also viewed these Accounting questions

Question

4. Are there any disadvantages?

Answered: 1 week ago

Question

3. What are the main benefits of using more information technology?

Answered: 1 week ago

Question

start to review and develop your employability skills

Answered: 1 week ago