The variance for activity G is closest to: a.10 b.12 c.14 d.16 e.18 f.20 g.22 h.None of the above The TF for activity F is
The variance for activity G is closest to:
a.10 b.12 c.14 d.16 e.18 f.20 g.22 h.None of the above
The TF for activity F is closest to:
a.0 b.1 c.2 d.3 e.4 f.5 g.6 h.7 i.None of the above
The expected project duration (Te) is closest to:
a. 90 b.95 c.100 d.105 e.110 f.115 g.120 h.125
The expected duration (weighted average) for activity H is closest to:
a. 27 b.36 c.40 d.45 e.50 f.55 g.60 h.163
The probability of finishing the project in the expected duration (Te) is closest to:
a. 100% b.90% c.80% d.70% e.60% f.50% g.40% h.30% i.20% j.10%
\begin{tabular}{|c|c|c|c} \hline Activity Name & Best Case & Most Likely & Worst Case \\ \hline A & 3 & 9 & 21 \\ \hline B & 24 & 30 & 60 \\ \hline C & 24 & 33 & 54 \\ \hline D & 21 & 24 & 33 \\ \hline E & 9 & 12 & 27 \\ \hline F & 21 & 30 & 45 \\ \hline G & 6 & 12 & 18 \\ \hline H & 27 & 36 & 63 \\ \hline I & 6 & 18 & 30 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started