The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data: - The
The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data: - The daily demand is 1700 units - The production lead time is 2 days - 2 day safety stock - One container fits 350 units How many kanban containers will be needed?