Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Thefollowing table shows the activities needed to complete a project along with precedences and activity durations (in weeks). The precedence column (headed Follows) shows which

Thefollowing table shows the activities needed to complete a project along with precedences and activity durations (in weeks). The precedence column (headed "Follows") shows which activities must be completed before given activity can begin.

Activity Follows Optimistic Duration Most Likely Duration Pessimistic Duration
A - 4 6 14
B A,C 3 4 5
C - 3 5 13
D A, E 12 18 24
E - 8 10 18
F A, E 4 6 8
G B,F 7 8 9
H G 10 12 14
I G 5 6 7
J D, I 5 7 9

a) Calculate mean duration and standard deviation for all the activities using the beta distribution. b) Construct a network diagram for this problem using the mean durations calculated in part (a), calculate the LS(Foll.), ES(Prec.) and total float for all the activities, and hence identify the critical path.What is the mean completion time for the project? What is the standard deviation of the critical path? c) What is the 92% confidence interval for the length of the critical path?

d) Assuming the probability distribution of the length of the critical path can be approximated by a normal distribution with the mean and standard deviation calculated in part (b), calculate the probability of completing the project within 42 weeks. e) Calculate the probability of completing the project between 35 and 40 weeks? f) If there is10.03% chance the project will take longer than X weeks- what figure should I give them (i.e. find X)?" [4]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sacred Mathematics Japanese Temple Geometry

Authors: Fukagawa Hidetoshi, Tony Rothman, Freeman Dyson

1st Edition

1400829712, 9781400829712

More Books

Students also viewed these Mathematics questions

Question

=+What are the factors and levels?

Answered: 1 week ago