There are four stations in a process: Station-1, Station-2, Station-3, and Station-4. Three products are produced in this process: Product-A, Product-B, and Product-C. The flow

There are four stations in a process: Station-1, Station-2, Station-3, and Station-4. Three products are produced in this process: Product-A, Product-B, and Product-C. The flow of the three products through 4 stations is shown in the process flow chart.

The total volume of production is 105 products per hour. Product-A is produced at a rate of 40 units per hour. Product-B is produced at a rate of 39 units per hour. The rest of the production is Product-C.

On average, there are 90 units of different products in this system.

There are 18 units of products in Station-1, 22 units of products in Station-2, 18 units of products in Station-3, and the rest are in Station-4.

Compute the flow time in station-4. Enter your answer in MINUTES with ONE decimal point.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability And Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson

14th Edition

0137476442, 978-0137476442

More Books

Students also viewed these General Management questions

Question

5-56. Trudy, when she first saw the bull pawing the ground, ran.

Answered: 1 week ago