There are two production lines line 1: line 2: line 1 produces 395 parts per day and has an average inventory of 400 parts. line
There are two production lines
\begin{tabular}{|c|c|c|} \hline Workstation & \# of Machines & Average Process Time (min) \\ \hline 1 & 6 & 6.2 \\ \hline 2 & 6 & 5.7 \\ \hline 3 & 4 & 4.2 \\ \hline 4 & 2 & 1.5 \\ \hline 5 & 2 & 2.3 \\ \hline 6 & 4 & 3.6 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|} \hline Workstation & \# of Machines & Average Process Time (min) \\ \hline 1 & 1 & 0.50 \\ \hline 2 & 1 & 0.48 \\ \hline 3 & 1 & 0.36 \\ \hline 4 & 1 & 0.42 \\ \hline \end{tabular} a. What is the Capacity per workstation for both lines? What is the Capacity per machine in each workstation for both lines? b. What workstation is the bottleneck for each line? Why? c. Calculate rb,To, and Wo for both lines. Which line has the larger critical WIP? Why line 1:
line 2:
line 1 produces 395 parts per day and has an average inventory of 400 parts.
line 2 produces 650 parts per day and has an aberage inventory of 300 parts.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started